electrical screw jack, manufacturing system, economic valueAbstract
The Dwi Hasta lifting crew jack is a tool that assist the car maintenance mechanician. It tool support the car at an elevation
for the maintenance working and lay it down after the mechanician done. The objective of study is to obtain the cost of the
manufacturing from production stage to selling. In which, it device is for assisting the mechanician repaired a car. Manufacture system would obtain economic values and production time at one unit. The investigation is started from design, and to the manufacturing system. Regards to the planning of the manufacturing, the production cost, the selling cost, and time of refund are obtained at the cost calculation. The money refund is the production cost will get after selling. The experiment method is conducted at operating process chart (OPC), manufacturing lead time (MLT), production time, production flow, production capacity and break event point (Q). The experiment results showed economic value from raw material to one-unit machine. MLT is of about 53,83 hours. Production time performs is for 346,7 min. Production capacity is 6 units per month. Break Event Point (Q) will be started after 3 months. The profit taking back is Rp 6.181. 964. Money will be payback after 3 month
References
N. I. Akbar, “Modifikasi Dongkrak Mekanik Menjadi Elektromekanik Kapasitas 2 Ton,” Univ. Pas., p. 37, 2016.
S. Islami and M. R. Fauzi, “Modifikasi Dongkrak Ulir Botol Menggunakan Motor Listrik,” J. Surya Tek., Vol. 9, no. 1, pp. 365–369, 2022, doi: 10.37859/jst.v9i1.3769.
M. Masshuri, “Modifikasi Dongkrak Screw Mekanis Menjadi Dongkrak Screw Elektrik Kapasitas 1 Ton Menggunakan Wireless Remote Control,” Mechonversio Mech. Eng. J., Vol. 2, No. 2, p. 63, 2020.
S. Ahmad., N. Tanti, dan T.G. Pandoyo. Perencanaan Gearbox dan Perhitungan Daya Motor pada Modifikasi Dongkrak Ulir Mekanis Menjadi Dongkrak Ulir Elektrik, Vol. 4 No. 2, 2013. Politeknik Negeri Balikpapan. Diakses 16 Maret 2021.
Cahyo., dan Sutowo. Analisa Dongkrak Ulir Dengan Beban 4000 kg. 2021. Universitas Muhammadiyah Jakarta. Diakses 15 Maret 2021.
M. Adek Ricky, T. Jhonnaidi, G. Tjahjono, dan I. Fahmi. Rancang Bangun Dongkrak Elektromekanik Menggunakan Motor Dc Berbasis Arduino Vol. 4 No. 1. 2019. Univ.Nusa Cendana. Diakses 28 Agustus 2021.
S. Ahmad S., N. Tanti, dan T.G. Pandoyo. Perencanaan Gearbox dan Perhitungan Daya Motor pada Modifikasi Dongkrak Ulir Mekanis Menjadi Dongkrak Ulir Elektrik, Vol. 4 No. 2, 2013. Politeknik Negeri Balikpapan. Diakses 16 Maret 2021.
D. Setiawan. Sistem kontrol motor DC menggunakan PWM berbasis Arduino. Vol. 15 No. 1, 2017. Universitas lancang kuning,. Diakses 23 Juli 2021.
R. M. Wattimena, A. S. Ardjo, Hartono, and A. S. Alfauzi, “Analisa Proses Manufaktur Di PT MAJ Sebagai Upaya Penyelarasan metode Pembelajaran Praktik Produksi Dalam Rangka Link & Match,” Pros. Semin. Has. Penelit. dan Pengabdi. Masy. Polines, pp. 1008–1018, 2020, [Online]. Available: https://jurnal.polines.ac.id/index.php/Sentrikom/article/download/2698/107490.
E. Supriyanto, “Manufaktur Dalam Dunia Teknik Industri,” J. Ind. Elektro dan Penerbangan, Vol. 3, No. 3, p. 1, 2020.
O. S. Produksi, “Operasi Manufaktur Overview,” Vol. 7, pp. 1–11. 2011.
T. Y. T. Kusuma dan M. F. S. Firdaus, “Penentuan Jumlah Tenaga Kerja Optimal untuk Peningkatan Produktifitas Kerja (Studi Kasus: UD. Rekayasa Wangdi W),” Integr. Lab J., Vol. 7, No. 2, pp. 26–36, 2019.
Downloads
Published
Issue
Section
License
This work is licensed under a Creative Commons Attribution-NonCommercial 4.0 International License.
Authors who publish with this journal agree to the following terms:
- Authors retain copyright and grant the journal right of first publication with the work simultaneously licensed under a Creative Commons: Attribution-NonCommercial 4.0 International (CC BY-NC) that allows others to share the work with an acknowledgement of the work's authorship and initial publication in this journal.
- Authors are able to enter into separate, additional contractual arrangements for the non-exclusive distribution of the journal's published version of the work (e.g., post it to an institutional repository or publish it in a book), with an acknowledgement of its initial publication in this journal.